I-10 Gas line Road to South of SR 387 Mileposts 177 – 187

  • Add third general-purpose lane in each direction within the existing median

  • Construct new interchange at Seed Farm Road

  • Reconstruct Pinal Avenue/SR387 interchange

  • Reconstruct and widen Gas Line Road bridge

  • Remove Dirk Lay Road bridge 

  • Improve infrastructure and install freeway management system: fiber optic cable, CCTV cameras and overhead message boards

Construction began in January 2026 and will last approximately two years, with an estimated construction cost of $267.9 million.

 

Contractor: FNF Construction, Inc.

Expected Construction Timeline Early 2026 – Mid 2028

20250129_I-10 WHP Corridor_Map_MASTER_I-10 WHP_Gasline Rd to Sth SR387_Short.png

Construction Updates

Drivers should watch for a new traffic configuration on I-10 just north of Casa Grande. Crews are shifting the existing two lanes of traffic to the outside lanes on eastbound I‑10 between Dirk Lay Road Bridge and SR 387/Pinal Ave. (Mileposts 177-187). They expect to have the new configuration fully in place by mid-May.

Crews are working overnight hours from 8 p.m. to 5 a.m. to get this work done. Lane restrictions related to the work can be found on the Traffic Alert page. Traffic Alerts

Later in May, drivers can expect crews to begin making the same shift to the westbound I-10 lanes in the same area.

These shifts will allow crews to begin constructing a third general‑purpose lane in the median. This traffic configuration will remain in place for about one year.

Diagram showing the traffic shift and emergency pull out lanes for five miles of eastbound and westbound I-10 between Dirk Lay Road and SR 387/Pinal Ave./SR 187